Take over of Medical Centre Construction Programme
Jun 30, 2025
Shore Construction seamlessly took over and completed the remaining works at St Peter’s Medical Centre, Brighton following the insolvency of the previous contractor, ensuring minimal disruption to project delivery and programme.
PROJECT SCOPE
The new Medical Centre replaces an existing Medical Centre for our client Medical Centre Developments Limited. Situated in a city centre location and serving a population with high levels of need, the centre supports a high-demand for mental health and substance misuse services.
To ensure continuity of care provision for the local community, the existing medical centre was required to remain open throughout the project.
Functioning as a GP medical practice, centre for the NHS Foundation Trust and with space for a proposed pharmacy, the new medical centre has four floors from ground through to 3rd floor.
Shore Construction became Main Contractor in November 2023, with the site in enforced closure following insolvency. The project supply chain was significantly impacted by financial loss from the original contractor requiring proactive management and communication.
PROACTIVE SOLUTIONS
Shore Construction became Main Contractor in November 2023, with the site in enforced closure following insolvency. The project supply chain was significantly impacted by financial loss from the original contractor requiring proactive management and communication.
By carefully coordinating mechanical and electrical installations, carpentry, floor finishes, and other internal works, they ensured a adhered to a tight programme, deliver high-quality results.
The phased construction approach allowed the existing Medical Centre to remain operational throughout the project, minimising disruption to services and maintaining continuous care for the community.
DELIVERY BENEFITS
EXPERT PROJECT MANAGEMENT
Smooth transition and completion of the project following contractor insolvency
PHASED IMPLEMENTATION
Uninterrupted healthcare services for the local population with phased programme
SUPPLY CHAIN ENGAGEMENT
Continuity of contractor works package delivery working with client and supply chain
COMMUNITY BENEFITS
Shore Construction worked with local tradesmen and sub-contractors including carpenters, electricians, plumbers, labourers, painters and decorators to maximse the economic benefit for the local community. This approach aligns with our brand ideal and social value programme.